| 132KV JOBAT | 335 | D8 | ALIRAJPUR | 33KV BORI | I | ON | 08 Dec 25 | 22:51:06 | 1.9103 | 22 Nov 25 | 11:01:06 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV FOOLMAL | IV | | | | | | | |
| 132KV JOBAT | 335 | D8 | ALIRAJPUR | 33KV KALIKHETIYAR | IV | ON | 08 Dec 25 | 22:51:05 | 2.6809 | 17 Nov 25 | 12:56:05 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV SONDWA | V | ON | 08 Dec 25 | 22:49:13 | 3.3314 | 19 Sep 25 | 12:00:16 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV FLOROSIS | V | ON | 08 Dec 25 | 22:49:14 | 3.972 | 15 Sep 25 | 19:48:13 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV AMBUA | V | ON | 08 Dec 25 | 22:49:14 | 10.116 | 11 Sep 25 | 22:35:14 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV NANPUR | V | ON | 08 Dec 25 | 22:49:17 | 3.9546 | 19 Sep 25 | 12:00:20 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV JOBAT | V | ON | 08 Dec 25 | 22:49:17 | 2.64 | 04 Sep 25 | 15:36:53 | 0 |
| 132KV JOBAT | 335 | D8 | ALIRAJPUR | 33KV JOBAT | V | ON | 08 Dec 25 | 22:51:04 | 6.2577 | 28 Sep 25 | 15:45:03 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV ALIRAJPUR | VII | ON | 08 Dec 25 | 22:49:16 | 3.1431 | 08 Sep 25 | 17:39:16 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV N.V.D.A. | VII-A | ON | 08 Dec 25 | 22:49:20 | 1.3951 | 08 Aug 25 | 06:29:20 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV JOBAT FATA DAM | VII-A | ON | 08 Dec 25 | 22:49:15 | 5.5941 | 08 Sep 25 | 11:42:15 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 132KV LIFT IRR. | zUG | ON | 08 Dec 25 | 22:49:21 | 10.7212 | 08 Aug 25 | 09:12:20 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV BUS COUPLER | zUG | ON | 08 Dec 25 | 22:49:19 | 3.0817 | 03 Dec 25 | 14:05:18 | 0 |
| 132KV JOBAT | 335 | D8 | ALIRAJPUR | 33KV DABRI | zUG | ON | 08 Dec 25 | 22:51:07 | 3.4746 | 07 Dec 25 | 09:13:06 | 0 |
| 132KV JOBAT | 335 | D8 | ALIRAJPUR | 33KV BUS COUPLER | zUG | OFF | 08 Dec 25 | 22:51:08 | 0 | 16 Jun 25 | 17:01:07 | 0 |
| Total | | | | | | | | | 62.2727 | | | 0 |
|
|
|
|
|
|
|