S/S NamessidalocationdistrictFeeder NameGroupfstatusDateTimePresent LoadSwitching DateSwitching TimeLoad Relief
132KV KANWAN111D6DHAR33KV BORALIION01 Mar 2612:05:121.9819 Feb 2608:15:160
132KV KANWAN111D6DHAR33KV BIDWALION01 Mar 2612:05:122.36417 Dec 2512:04:130
132KV KANWAN111D6DHAR33KV CHAYANION01 Mar 2612:05:143.34815 Jan 2616:00:150
132KV KANWAN111D6DHAR33KV RAJODION01 Mar 2612:05:151.56410 Jan 2609:19:290
132KV MANAWAR109D6DHAR33KV KAROLIION04 Feb 2614:30:13020 Sep 2509:46:120
132KV MANAWAR109D6DHAR33KV TONKIION04 Feb 2614:29:23008 Oct 2522:10:200
132KV RAJGARH105D6DHAR33KV DATTIGAONION08 Feb 2600:12:13008 Nov 2517:00:140
132KV RAJGARH105D6DHAR33KV RAJODION08 Feb 2600:12:14020 Oct 2517:45:150
132KV RAJGARH105D6DHAR33KV DASAIION08 Feb 2600:12:15009 Nov 2508:13:160
220KV DHAR103D6DHAR33KV SEJWOYAION22 Feb 2618:14:14021 Feb 2619:04:160
132KV BAGDI214D6DHAR33KV KUNJRODIION01 Mar 2611:54:142.00412 Dec 2515:28:130
132KV BARWANI110D6DHAR33KV NISARPURIION01 Mar 2611:49:120.58821 Feb 2601:24:130
132KV DHAMNOD98D6DHAR33KV GUJARIIION01 Mar 2612:13:142.7628 Feb 2611:49:150
132KV MANAWAR109D6DHAR33KV BAKANERIION04 Feb 2614:29:18020 Sep 2509:43:240
132KV MANAWAR109D6DHAR33KV DHARAMPURIIION04 Feb 2614:29:19008 Oct 2522:08:170
132KV MANAWAR109D6DHAR33KV UMARBANIION04 Feb 2614:30:18008 Oct 2522:08:180
132KV RAJGARH105D6DHAR33KV AMZERAIIOFF08 Feb 2600:12:12022 Jan 2611:13:120
220KV BADNAGAR56D6DHAR33KV MULTHANIION01 Mar 2612:06:121.41619 Feb 2611:48:300
220KV DHAR103D6DHAR33KV NARAYANPURAIION22 Feb 2618:14:12002 Jan 2611:20:130
220KV KUKSHI106D6DHAR33KV BHAWARIYAIION01 Mar 2612:08:067.531322 Feb 2616:53:090
132KV KANWAN111D6DHAR33KV NAGDAIIION01 Mar 2612:05:143.51621 Feb 2612:51:160
132KV MANAWAR109D6DHAR33KV SINGHANAIIION04 Feb 2614:30:14020 Sep 2509:43:220
132KV SINGHANA339D6DHAR33KV LOHARIIIION01 Mar 2611:56:044.906920 Feb 2609:29:050
220KV DHAR103D6DHAR33KV TEESGAONIIION22 Feb 2618:14:13001 Feb 2614:44:140
220KV DHAR103D6DHAR33KV BERCHAIIION22 Feb 2618:14:14021 Feb 2620:43:150
220KV DHAR103D6DHAR33KV KALIKADEVIIIION22 Feb 2618:14:15004 Feb 2616:19:170
220KV RAJGARH2112D6DHAR33KV RINGNODIIION02 Jan 2611:55:14030 Dec 2513:46:140
132KV BAGDI214D6DHAR33KV BAGDIIVON01 Mar 2611:54:141.8608 Jan 2623:43:130
132KV BAGDI214D6DHAR33KV MANDUIVON01 Mar 2611:54:130.98421 Sep 2513:20:130
132KV BAGDI214D6DHAR33KV NALCHHAIVON01 Mar 2611:54:131.89619 Feb 2601:29:130
132KV CHHOTIKHARGONE116D6DHAR33KV SUNDRELIVOFF01 Mar 2611:52:140.000630 Apr 2515:44:140
132KV GHATABILLOD107D6DHAR33KV KESUR-IIVOFF01 Mar 2611:55:130.003304 Oct 2502:03:130
132KV GHATABILLOD107D6DHAR33KV KESUR-IIIVON01 Mar 2611:55:145.49628 Jan 2622:00:140
132KV GHATABILLOD107D6DHAR33KV NEKPURIVON01 Mar 2611:55:143.07220 Jan 2613:28:150
132KV GHATABILLOD107D6DHAR33KV PANKHEDIIVON01 Mar 2611:55:154.272301 Feb 2609:47:160
132KV KANWAN111D6DHAR33KV KARODIVON01 Mar 2612:05:132.8213 Dec 2515:03:140
132KV MANAWAR109D6DHAR33KV AJANDAIVON04 Feb 2614:30:15020 Sep 2509:46:140
132KV SINGHANA339D6DHAR33KV SINGHANAIVON01 Mar 2611:56:0211.670222 Feb 2612:45:040
132KV SINGHANA339D6DHAR33KV JHAPDIIVON01 Mar 2611:56:038.071927 Jan 2613:23:040
220KV DHAR103D6DHAR33KV AHOOIVON22 Feb 2618:14:15020 Feb 2618:31:170
220KV DHAR103D6DHAR33KV DEDLAIVON22 Feb 2618:14:12007 Feb 2617:19:120
220KV KANWAN2376D6DHAR33KV TAKRAWDAIVON01 Mar 2612:01:041.54723 Feb 2604:04:060
220KV KUKSHI106D6DHAR33KV BAGHIVON01 Mar 2612:08:033.701426 Feb 2612:06:040
220KV KUKSHI106D6DHAR33KV DEHRIIVON01 Mar 2612:08:042.540224 Feb 2606:05:040
220KV KUKSHI106D6DHAR33KV DHOLIYAIVON01 Mar 2612:08:080.719720 Feb 2609:47:080
220KV KUKSHI106D6DHAR33KV NISARPURIVON01 Mar 2612:08:090.641711 Feb 2617:55:090
220KV RAJGARH2112D6DHAR33KV TANDAIVON02 Jan 2611:55:15009 Dec 2510:54:180
220KV RAJGARH2112D6DHAR33KV HATODIVON02 Jan 2611:55:13030 Dec 2514:22:140
132KV DHAMNOD98D6DHAR33KV DHAMNODVON01 Mar 2612:13:123.142806 Feb 2611:47:130
132KV MANAWAR109D6DHAR33KV MANAWARVON04 Feb 2614:30:20008 Oct 2522:08:200
220KV BADNAGAR56D6DHAR33KV BADNAWARV-AON01 Mar 2612:06:121.3810 Feb 2614:22:120
220KV KUKSHI106D6DHAR33KV SUSARIVION01 Mar 2612:08:108.889126 Feb 2615:44:100
132KV MANAWAR109D6DHAR33KV JEERABADVI-AON04 Feb 2614:29:18027 Sep 2511:49:150
220KV KUKSHI106D6DHAR33KV DAHIVI-AON01 Mar 2612:08:078.116901 Mar 2611:47:080
220KV PITHAMPUR_SEC1104D6DHAR33KV COSMOS LUNAWATVI-AOFF01 Mar 2611:57:210.000125 Feb 2619:37:200
132KV KANWAN111D6DHAR33KV OASISVIION01 Mar 2612:05:132.99619 Feb 2613:44:140
132KV NETRIP389D6DHAR33KV KUNWARSIVIION01 Mar 2612:03:041.717920 Feb 2602:14:040
132KV NETRIP389D6DHAR33KV KHANDWA KHEDAVIION01 Mar 2612:03:055.884420 Jan 2613:29:030
220KV DHAR103D6DHAR33KV DHARVIION22 Feb 2618:14:13025 Jan 2608:33:130
220KV DHAR103D6DHAR33KV DASHARA MAIDANVIION22 Feb 2618:14:16011 Feb 2601:45:160
220KV PITHAMPUR_SEC3102D6DHAR33KV SAGOREVIION01 Mar 2612:02:200.08401 Mar 2607:50:210
132KV MANAWAR109D6DHAR33KV D.C.L.VII-AON04 Feb 2614:30:19028 Sep 2506:02:170
132KV RAJGARH105D6DHAR33KV P.H.E.VII-AON08 Feb 2600:12:13006 Nov 2506:50:130
132KV SINGHANA339D6DHAR33KV BARKHEDAVII-AOFF06 Nov 2522:11:07002 Nov 2512:28:080
220KV KUKSHI106D6DHAR33KV P.H.E.VII-AOFF01 Mar 2612:08:110.000513 Feb 2604:11:120
220KV KUKSHI106D6DHAR33KV WATER WORKSVII-AON01 Mar 2612:08:0511.51326 Feb 2608:18:050
220KV PITHAMPUR_SEC1104D6DHAR33KV SAGOREVII-AON01 Mar 2611:57:162.78420 Feb 2601:02:160
220KV PITHAMPUR_SEC3102D6DHAR33KV L.T.INDUSTRIESVII-AON01 Mar 2612:02:195.13628 Feb 2615:15:190
220KV RAJGARH2112D6DHAR33KV P.G.C.I.L.VII-AON02 Jan 2611:55:16026 Oct 2514:25:190
132KV DHAMNOD98D6DHAR33KV BPCLwIXON01 Mar 2612:13:131.62801 Feb 2615:00:130
132KV DHAMNOD98D6DHAR33KV INDUSTRIALwIXON01 Mar 2612:13:153.925331 Jan 2616:04:160
132KV GHATABILLOD107D6DHAR33KV INDUSTRIALwIXON01 Mar 2611:55:136.85231 Jan 2612:00:140
132KV RAJGARH105D6DHAR33KV INDUSTRIALwIXON08 Feb 2600:12:12005 Dec 2511:06:120
220KV DHAR103D6DHAR33KV INDUSTRIALwIXON22 Feb 2618:14:16022 Feb 2618:12:170
220KV KANWAN2376D6DHAR33KV IHB INDRAWALwIXON01 Mar 2612:01:050.04627 Feb 2618:19:050
220KV PITHAMPUR_SEC1104D6DHAR33KV KRITI INDUS.wIXON01 Mar 2611:57:186.126725 Feb 2622:00:180
220KV PITHAMPUR_SEC3102D6DHAR33KV SEZ-IwIXON01 Mar 2612:02:189.66231 Oct 2518:24:170
220KV PITHAMPUR_SEC3102D6DHAR33KV SEZ-IIwIXON01 Mar 2612:02:184.83820 Feb 2601:41:030
220KV PITHAMPUR_SEC3102D6DHAR33KV MITTAL CORP2wIXON01 Mar 2612:02:1915.7228 Feb 2600:15:200
220KV PITHAMPUR_SEC3102D6DHAR33KV SEZ-IIIwIXOFF01 Mar 2612:02:16011 Dec 2414:15:150
220KV PITHAMPUR_SEC3102D6DHAR33KV AARTI INDUSTRYwIXON01 Mar 2612:02:242.367606 Jan 2616:48:240
132KV GHATABILLOD107D6DHAR33KV NATIONAL STEELXON01 Mar 2611:55:127.34422 Sep 2509:14:150
132KV GHATABILLOD107D6DHAR33KV MSPXON01 Mar 2611:55:124.022721 Sep 2513:26:120
220KV PITHAMPUR_SEC3102D6DHAR33KV RATHI STEELXON01 Mar 2612:02:213.8419 Feb 2600:26:360
132KV BAGDI214D6DHAR33KV INDUSTRIAL-IXIIION01 Mar 2611:54:161.681518 Dec 2516:05:160
132KV BAGDI214D6DHAR33KV INDUSTRIAL-IIXIIION01 Mar 2611:54:170.354721 Sep 2515:44:210
220KV PITHAMPUR_SEC1104D6DHAR33KV KINETIC HONDAXIIION01 Mar 2611:57:166.80425 Feb 2618:24:170
220KV PITHAMPUR_SEC1104D6DHAR33KV NICHOLASXIIION01 Mar 2611:57:196.755828 Feb 2616:23:210
220KV PITHAMPUR_SEC1104D6DHAR33KV RAJSHREEXIIION01 Mar 2611:57:207.802122 Feb 2611:47:200
220KV PITHAMPUR_SEC1104D6DHAR33KV BAJAJ TEMPOXIIIOFF01 Mar 2611:57:130.002501 Mar 2608:06:130
220KV PITHAMPUR_SEC1104D6DHAR33KV PRESTIGE METALXIIION01 Mar 2611:57:134.73126 Feb 2611:08:130
220KV PITHAMPUR_SEC1104D6DHAR33KV EICHERXIIION01 Mar 2611:57:146.72725 Feb 2614:50:130
220KV PITHAMPUR_SEC1104D6DHAR33KV L.T.INDUSTRIESXIIION01 Mar 2611:57:159.67506 Feb 2607:07:140
220KV PITHAMPUR_SEC1104D6DHAR33KV RAJRATANXIIION01 Mar 2611:57:154.58425 Feb 2616:11:150
220KV PITHAMPUR_SEC3102D6DHAR33KV METALMAN-IXIIION01 Mar 2612:02:130.37127 Feb 2617:24:130
220KV PITHAMPUR_SEC3102D6DHAR33KV METALMAN-IIXIIION01 Mar 2612:02:137.4401 Mar 2601:18:130
220KV PITHAMPUR_SEC3102D6DHAR33KV GIRNARXIIION01 Mar 2612:02:149.01528 Feb 2617:34:140
220KV PITHAMPUR_SEC3102D6DHAR33KV CHIRAGXIIION01 Mar 2612:02:142.6419 Feb 2600:50:170
220KV PITHAMPUR_SEC3102D6DHAR33KV NOVINOXIIION01 Mar 2612:02:154.036626 Feb 2615:08:180
220KV PITHAMPUR_SEC3102D6DHAR33KV PRATIBHAXIIION01 Mar 2612:02:166.33626 Feb 2615:57:180
220KV PITHAMPUR_SEC3102D6DHAR33KV SRFXIIIOFF01 Mar 2612:02:220.000401 Mar 2611:45:220
220KV PITHAMPUR_SEC3102D6DHAR33KV SHIVANGIXIIION01 Mar 2612:02:238.545620 Feb 2613:45:270
220KV PITHAMPUR_SEC3102D6DHAR33KV AKVN-IXIIION01 Mar 2612:02:258.641520 Feb 2601:01:250
220KV PITHAMPUR_SEC3102D6DHAR33KV AKVN-IIXIIION01 Mar 2612:02:266.16118 Jan 2615:45:260
132KV BAGDI214D6DHAR33KV BUS COUPLERzUGON01 Mar 2611:54:152.83227 Sep 2513:11:150
132KV CHHAYAN345D6DHAR33KV HEADQUARTERzUGON01 Mar 2612:02:041.798725 Feb 2615:27:030
132KV CHHAYAN345D6DHAR33KV HANUMANTIYAzUGON01 Mar 2612:02:052.938104 Jan 2605:02:040
132KV CHHAYAN345D6DHAR33KV NANDLAIzUGON01 Mar 2612:02:061.904214 Feb 2616:11:070
132KV CHHAYAN345D6DHAR33KV BUS COUPLERzUGOFF01 Mar 2612:02:070.000125 Sep 2510:41:050
132KV CHHAYAN345D6DHAR33KV TILGARAzUGON01 Mar 2612:01:086.400927 Sep 2516:44:070
132KV DHAMNOD98D6DHAR33KV N.V.D.A.zUGON01 Mar 2612:13:153.88823 Feb 2612:18:160
132KV DHAMNOD98D6DHAR33KV BUS COUPLERzUGOFF01 Mar 2612:13:16019 Sep 2512:57:160
132KV GHATABILLOD107D6DHAR33KV BUS COUPLERzUGON01 Mar 2611:55:163.924803 Jan 2602:52:170
132KV MANAWAR109D6DHAR132KV ULTRATECHzUGON04 Feb 2614:30:23011 Sep 2508:12:540
132KV MANAWAR109D6DHAR33KV SATGURU CEMENTSzUGON04 Feb 2614:30:24020 Sep 2509:43:330
132KV MANAWAR109D6DHAR33KV BUS COUPLERzUGOFF04 Feb 2614:30:22018 Aug 2519:57:220
132KV NETRIP389D6DHAR33KV BUS COUPLERzUGOFF01 Mar 2612:03:06013 Mar 2521:14:040
132KV NETRIP389D6DHAR33KV S.I.P.-IzUGON01 Mar 2612:03:074.89512 Jan 2609:22:060
132KV NETRIP389D6DHAR33KV S.I.P.-IIzUGON01 Mar 2612:03:0815.39831 Oct 2508:26:060
132KV RAJGARH105D6DHAR33KV BOLAzUGON08 Feb 2600:12:17027 Oct 2518:15:180
132KV RAJGARH105D6DHAR33KV BHANGARHzUGON08 Feb 2600:12:18013 Dec 2507:40:180
132KV RAJGARH105D6DHAR33KV BUS COUPLERzUGON08 Feb 2600:12:16013 Dec 2510:34:170
132KV SINGHANA339D6DHAR33KV GANDHWANIzUGON01 Mar 2611:56:054.057414 Dec 2518:57:080
132KV SINGHANA339D6DHAR33KV BUS COUPLERzUGOFF06 Nov 2522:11:06025 Sep 2512:20:100
132KV TEESGAON375D6DHAR33KV BUS COUPLERzUGOFF01 Mar 2612:04:050.000112 Dec 2513:55:060
132KV TEESGAON375D6DHAR33KV BERCHHAzUGON01 Mar 2612:04:043.041307 Feb 2611:41:040
132KV TEESGAON375D6DHAR33KV TEESGAONzUGON01 Mar 2612:04:032.153512 Dec 2513:55:040
220KV BADNAGAR56D6DHAR33KV KACHHIBARODAzUGON01 Mar 2612:06:240.488821 Feb 2613:10:240
220KV DHAR103D6DHAR132KV VACMETzUGON22 Feb 2618:14:20015 Sep 2502:47:210
220KV DHAR103D6DHAR132KV B/C VACMETzUGOFF22 Feb 2618:14:21020 Jun 2215:04:220
220KV DHAR103D6DHAR33KV BHOJ ASPATALzUGON22 Feb 2618:14:22003 Nov 2511:57:220
220KV DHAR103D6DHAR33KV NEW BUS COUPLERzUGOFF22 Feb 2618:14:17003 Feb 2619:49:180
220KV DHAR103D6DHAR33KV BUS COUPLERzUGOFF22 Feb 2618:14:18024 Feb 2516:00:180
220KV DHAR103D6DHAR33KV TIRLAzUGON22 Feb 2618:14:19022 Feb 2612:19:200
220KV KANWAN2376D6DHAR33KV NAGDAzUGON01 Mar 2612:01:024.804519 Feb 2610:06:030
220KV KANWAN2376D6DHAR33KV TRANSFER BAYzUGOFF01 Mar 2612:01:030.000122 Jan 2616:04:060
220KV KUKSHI106D6DHAR33KV BUS COUPLERzUGOFF01 Mar 2612:08:120.000823 Feb 2606:43:120
220KV PITHAMPUR_SEC1104D6DHAR33KV BUS COUPLERzUGOFF01 Mar 2611:57:17030 Jan 2612:49:170
220KV PITHAMPUR_SEC3102D6DHAR33KV NEW BUS COUPLERzUGOFF01 Mar 2612:02:17027 Feb 2617:24:200
220KV PITHAMPUR_SEC3102D6DHAR33KV BUS COUPLER-IIIzUGOFF01 Mar 2612:02:24026 Feb 2616:00:280
220KV PITHAMPUR_SEC3102D6DHAR33KV BUS COUPLER-IzUGOFF01 Mar 2612:02:20020 Feb 2613:45:250
220KV RAJGARH2112D6DHAR33KV AKVN-IIzUGON02 Jan 2611:55:13028 Dec 2512:04:140
220KV RAJGARH2112D6DHAR33KV BADODIYAzUGON02 Jan 2611:55:17013 Dec 2514:15:180
220KV RAJGARH2112D6DHAR33KV AKVN-IzUGON02 Jan 2611:55:18006 Dec 2513:29:180
220KV RAJGARH2112D6DHAR33KV BUS COUPLERzUGOFF02 Jan 2611:55:19024 Dec 2512:23:200
Total        360.1225  0