MADHYA PRADESH PASCHIM KSHETRA VIDYUT VITARAN CO. LTD.
|
|
|
|
CURRENT LOAD DETAILS OF 33KV FEEDERS COMES UNDER GROUP (VII-A) IN KHARGONE district
- SORTED BY
| S/S Name | ssid | alocation | district | Feeder Name | Group | fstatus | Date | Time | Present Load | Switching Date | Switching Time | Load Relief |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV GYASPURA | VII-A | ON | 24 Nov 26 | 20:06:08 | 0.0242 | 29 Sep 26 | 09:06:09 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV MOHAMMADPUR | VII-A | ON | 24 Nov 26 | 20:06:09 | 0.0254 | 02 Sep 26 | 12:51:09 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV BADIYA PH-5 | VII-A | ON | 24 Nov 26 | 20:06:10 | 1.9359 | 23 Aug 26 | 18:57:10 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV REHGAON PH | VII-A | ON | 24 Nov 26 | 20:06:11 | 4.4897 | 12 Nov 26 | 13:10:11 | 0 |
| 132KV KASRAWAD | 229 | D4 | KHARGONE | 33KV BALAKWADA | VII-A | ON | 24 Nov 26 | 20:06:20 | 3.1297 | 12 Nov 26 | 16:28:25 | 0 |
| 132KV KASRAWAD | 229 | D4 | KHARGONE | 33KV INDUSTRIAL | VII-A | ON | 24 Nov 26 | 20:03:13 | 1.358 | 18 Nov 26 | 05:17:14 | 0 |
| 132KV KASRAWAD | 229 | D4 | KHARGONE | 33KV BHANGAON | VII-A | ON | 24 Nov 26 | 20:06:18 | 0.792 | 12 Nov 26 | 16:28:23 | 0 |
| 132KV KHARGONE | 119 | D4 | KHARGONE | 33KV SOOT MILL | VII-A | ON | 24 Nov 26 | 20:06:15 | 2.197 | 19 Nov 26 | 14:52:16 | 0 |
| 132KV SANAWAD | 126 | D4 | KHARGONE | 33KV KHARGONE TRANS. | VII-A | ON | 24 Nov 26 | 20:05:18 | 2.1456 | 21 Nov 26 | 14:13:18 | 0 |
| 132KV TALAKPURA | 337 | D4 | KHARGONE | 33KV LEHKU | VII-A | ON | 24 Nov 26 | 20:05:10 | 3.4481 | 21 Nov 26 | 02:21:09 | 0 |
| 220KV BARWAHA | 114 | D4 | KHARGONE | 33KV LIFT IRRIGATION | VII-A | ON | 26 Feb 26 | 17:38:16 | 0 | 28 Jan 26 | 20:33:17 | 0 |
| 220KV BARWAHA | 114 | D4 | KHARGONE | 33KV P.S.1 SASLIYA | VII-A | OFF | 13 Mar 26 | 10:30:17 | 0 | 13 Feb 26 | 11:43:26 | 0 |
| Total | | | | | | | | | 19.5456 | | | 0 |
|
|
|
|
|
|
|