MADHYA PRADESH PASCHIM KSHETRA VIDYUT VITARAN CO. LTD.
|
|
|
|
CURRENT LOAD DETAILS OF 33KV FEEDERS COMES UNDER GROUP (VII-A)
- SORTED BY
| S/S Name | ssid | alocation | district | Feeder Name | Group | fstatus | Date | Time | Present Load | Switching Date | Switching Time | Load Relief |
| 132KV BALWADA | 277 | D1 | INDORE | 33KV P.S.2 GAWALU | VII-A | ON | 10 Sep 26 | 20:59:06 | 2.1409 | 06 Apr 26 | 14:11:06 | 0 |
| 132KV BALWADA | 277 | D1 | INDORE | 33KV P.S.3 BHERUGHAT | VII-A | ON | 10 Sep 26 | 20:59:07 | 2.3789 | 08 Aug 26 | 17:19:07 | 0 |
| 132KV BETMA | 221 | D1 | INDORE | 33KV IT PARK-I | VII-A | ON | 10 Sep 26 | 21:10:15 | 3.8813 | 21 Jul 26 | 10:15:15 | 0 |
| 132KV BETMA | 221 | D1 | INDORE | 33KV IT PARK-II | VII-A | ON | 10 Sep 26 | 21:10:16 | 1.1162 | 14 Aug 26 | 06:53:16 | 0 |
| 132KV JAMLI | 129 | D1 | INDORE | 33KV PHE | VII-A | ON | 10 Sep 26 | 21:01:18 | 1.0609 | 02 Sep 26 | 22:24:18 | 0 |
| 132KV NAVDAPANTH | 194 | D1 | INDORE | 33KV AIRPORT | VII-A | ON | 10 Sep 26 | 21:01:16 | 1.2177 | 23 Aug 26 | 12:50:19 | 0 |
| 132KV SATYASAI | 99 | D1 | INDORE | 33KV REDISSON | VII-A | OFF | 26 Dec 24 | 14:49:13 | 0 | 24 Dec 24 | 11:15:13 | 0 |
| 132KV SIMROL | 267 | D1 | INDORE | 33KV I.I.T. | VII-A | ON | 10 Sep 26 | 21:03:08 | 1.8124 | 21 Aug 26 | 02:45:05 | 0 |
| 220KV BARWAHA | 114 | D1 | INDORE | 33KV P.S.2 GAWALU | VII-A | OFF | 12 Mar 26 | 15:17:18 | 0 | 30 Oct 25 | 10:45:19 | 0 |
| 220KV BARWAHA | 114 | D1 | INDORE | 33KV P.S.3 BHERUGHAT | VII-A | OFF | 12 Mar 26 | 11:48:19 | 0 | 12 Mar 26 | 11:32:20 | 0 |
| 220KV INDORE_NORTH | 92 | D1 | INDORE | 33KV RAMAPHOSPHATE | VII-A | ON | 10 Sep 26 | 20:58:12 | 3.504 | 08 Sep 26 | 13:28:12 | 0 |
| 220KV JAITPURA | 100 | D1 | INDORE | 33KV RAMAPHOSPHATE | VII-A | ON | 10 Sep 26 | 20:30:15 | 3.183 | 18 Aug 26 | 17:26:15 | 0 |
| 132KV DEWAS_MSP | 65 | D10 | DEWAS | 33KV NEW MSP | VII-A | ON | 10 Sep 26 | 20:57:27 | 4.8437 | 14 Jun 26 | 12:28:22 | 0 |
| 132KV KANNOD | 70 | D10 | DEWAS | 33KV M.S.K. | VII-A | ON | 10 Sep 26 | 20:59:02 | 1.3142 | 27 Jun 26 | 18:19:02 | 0 |
| 132KV KHATEGAON | 196 | D10 | DEWAS | 33KV M.S.K. | VII-A | ON | 31 Aug 26 | 12:56:12 | 0 | 05 Aug 26 | 02:33:13 | 0 |
| 132KV SONKATCH | 71 | D10 | DEWAS | 33KV NVDA (TALOD) | VII-A | OFF | 10 Sep 26 | 21:01:20 | 0.0002 | | | 0 |
| 220KV CHAPDA | 67 | D10 | DEWAS | 33KV N.V.D.A. | VII-A | ON | 10 Sep 26 | 21:00:24 | 0.0291 | 09 Sep 26 | 17:29:26 | 0 |
| 220KV DEWAS | 63 | D10 | DEWAS | 33KV LAKSHMI SOLVEX | VII-A | ON | 10 Sep 26 | 21:13:14 | 3.996 | 10 Sep 26 | 02:11:13 | 0 |
| 132KV MAXI | 75 | D11 | SHAJAPUR | 33KV WATER WORKS | VII-A | ON | 10 Sep 26 | 21:02:12 | 0.1689 | 18 Aug 26 | 20:49:32 | 0 |
| 132KV RATLAM | 80 | D12 | RATLAM | 33KV J.V.L. | VII-A | ON | 10 Sep 26 | 21:00:13 | 6.1701 | 24 Aug 26 | 11:50:12 | 0 |
| 132KV RATLAM | 80 | D12 | RATLAM | 33KV DHOLAWAD | VII-A | ON | 10 Sep 26 | 21:00:19 | 2.2027 | 31 Jul 26 | 17:35:19 | 0 |
| 132KV RATLAM | 80 | D12 | RATLAM | 33KV MEDICAL COLLEGE | VII-A | ON | 10 Sep 26 | 21:00:20 | 0.5117 | 30 May 26 | 12:03:19 | 0 |
| 220KV JAORA | 77 | D12 | RATLAM | 33KV AMBIKA SOLVEX | VII-A | ON | 10 Sep 26 | 21:02:05 | 2.0658 | 09 Sep 26 | 18:28:05 | 0 |
| 220KV RATLAM2 | 78 | D12 | RATLAM | 33KV I.O.C.L. | VII-A | ON | 10 Sep 26 | 21:01:18 | 1.5329 | 09 Sep 26 | 17:08:19 | 0 |
| 132KV MANDSAUR | 82 | D13 | MANDSAUR | 33KV RAJARAM | VII-A | ON | 10 Sep 26 | 21:01:05 | 1.4051 | 18 Aug 26 | 18:33:05 | 0 |
| 132KV MANDSAUR | 82 | D13 | MANDSAUR | 33KV SONI BIOCHEM | VII-A | ON | 10 Sep 26 | 21:01:07 | 1.0119 | 03 Apr 26 | 00:19:08 | 0 |
| 220KV DALODA | 85 | D13 | MANDSAUR | 33KV RUCHI SOYA | VII-A | ON | 10 Sep 26 | 20:59:12 | 10.704 | 01 Sep 26 | 04:42:12 | 0 |
| 132KV SUSNER | 60 | D15 | AGAR | 33KV PUMP HOUSE-2 | VII-A | ON | 10 Sep 26 | 21:01:19 | 0.029 | 30 Aug 26 | 10:32:20 | 0 |
| 220KV NALKHEDA | 297 | D15 | AGAR | 33KV PUMP HOUSE-4 | VII-A | ON | 10 Sep 26 | 20:44:08 | 0.0206 | 15 Jul 26 | 10:41:08 | 0 |
| 220KV NALKHEDA | 297 | D15 | AGAR | 33KV JAL NIGAM | VII-A | ON | 10 Sep 26 | 20:44:10 | 1.0499 | 10 Sep 26 | 09:13:09 | 0 |
| 132KV CHHEGAON | 117 | D2 | KHANDWA | 33KV KHANDWA-II | VII-A | ON | 10 Sep 26 | 20:57:07 | 1.347 | 15 Jul 26 | 13:38:06 | 0 |
| 132KV KHANDWA | 115 | D2 | KHANDWA | 33KV N.V.D.A. | VII-A | ON | 10 Sep 26 | 21:01:17 | 0.0268 | 29 Jul 26 | 14:22:17 | 0 |
| 132KV KHANDWA | 115 | D2 | KHANDWA | 33KV RAILWAY STATION | VII-A | ON | 10 Sep 26 | 21:01:18 | 2.0304 | 23 Jun 26 | 03:45:19 | 0 |
| 132KV KHANDWA | 115 | D2 | KHANDWA | 33KV PGCIL | VII-A | ON | 10 Sep 26 | 21:01:20 | 0.1978 | 28 Jul 26 | 14:43:21 | 0 |
| 132KV KHANDWA | 115 | D2 | KHANDWA | 33KV CHANDEL-I | VII-A | ON | 10 Sep 26 | 21:01:24 | 1.2993 | 29 Jul 26 | 10:56:32 | 0 |
| 132KV KHANDWA | 115 | D2 | KHANDWA | 33KV CHANDEL-II | VII-A | ON | 03 May 25 | 00:00:24 | 0 | 01 May 25 | 09:21:35 | 0 |
| 132KV MOONDI | 258 | D2 | KHANDWA | 33KV DEVLA | VII-A | ON | 10 Sep 26 | 20:56:13 | 1.068 | 06 Sep 26 | 15:36:13 | 0 |
| 132KV MOONDI | 258 | D2 | KHANDWA | 33KV NARMADA NAGAR | VII-A | ON | 10 Sep 26 | 20:56:13 | 4.395 | 20 Aug 26 | 18:09:14 | 0 |
| 132KV SANAWAD | 126 | D2 | KHANDWA | 33KV NHDC | VII-A | ON | 10 Sep 26 | 21:01:16 | 0.855 | 02 Sep 26 | 16:16:15 | 0 |
| 220KV CHANNERA | 215 | D2 | KHANDWA | 33KV NANDGAON | VII-A | OFF | 10 Sep 26 | 20:59:13 | 0.022 | 10 Sep 26 | 09:12:13 | 0 |
| 220KV CHANNERA | 215 | D2 | KHANDWA | 33KV CHARKHEDA | VII-A | ON | 10 Sep 26 | 20:59:13 | 0.035 | 05 Sep 26 | 17:29:13 | 0 |
| 220KV CHANNERA | 215 | D2 | KHANDWA | 33KV AWALIYA | VII-A | ON | 10 Sep 26 | 20:59:14 | 2.472 | 10 Sep 26 | 17:25:15 | 0 |
| 220KV CHHEGAON2 | 234 | D2 | KHANDWA | 33KV NVDA (ROHANI) | VII-A | ON | 10 Sep 26 | 21:01:16 | 0.018 | 27 Jun 26 | 16:20:17 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV GYASPURA | VII-A | ON | 10 Sep 26 | 21:02:08 | 0.0205 | 02 Sep 26 | 12:51:08 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV MOHAMMADPUR | VII-A | ON | 10 Sep 26 | 21:02:09 | 0.0223 | 02 Sep 26 | 12:51:09 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV BADIYA PH-5 | VII-A | ON | 10 Sep 26 | 21:02:10 | 0.0108 | 23 Aug 26 | 18:57:10 | 0 |
| 132KV ANDAD | 329 | D4 | KHARGONE | 33KV REHGAON PH | VII-A | ON | 10 Sep 26 | 21:02:11 | 0.8506 | 02 Sep 26 | 12:50:12 | 0 |
| 132KV KASRAWAD | 229 | D4 | KHARGONE | 33KV INDUSTRIAL | VII-A | OFF | 10 Sep 26 | 21:01:13 | 0.03 | 27 Jun 26 | 17:41:14 | 0 |
| 132KV KASRAWAD | 229 | D4 | KHARGONE | 33KV BHANGAON | VII-A | ON | 10 Sep 26 | 21:01:16 | 0.6131 | 24 Aug 26 | 03:43:16 | 0 |
| 132KV KASRAWAD | 229 | D4 | KHARGONE | 33KV BALAKWADA | VII-A | ON | 10 Sep 26 | 21:01:18 | 0.0366 | 22 Aug 26 | 07:19:22 | 0 |
| 132KV KHARGONE | 119 | D4 | KHARGONE | 33KV SOOT MILL | VII-A | ON | 10 Sep 26 | 20:59:15 | 0.098 | 28 Aug 26 | 10:46:17 | 0 |
| 132KV SANAWAD | 126 | D4 | KHARGONE | 33KV KHARGONE TRANS. | VII-A | ON | 10 Sep 26 | 21:01:18 | 2.8182 | 04 Sep 26 | 10:17:17 | 0 |
| 132KV TALAKPURA | 337 | D4 | KHARGONE | 33KV LEHKU | VII-A | ON | 10 Sep 26 | 21:01:09 | 0.0197 | 13 Aug 26 | 03:42:09 | 0 |
| 220KV BARWAHA | 114 | D4 | KHARGONE | 33KV LIFT IRRIGATION | VII-A | ON | 26 Feb 26 | 17:38:16 | 0 | 28 Jan 26 | 20:33:17 | 0 |
| 220KV BARWAHA | 114 | D4 | KHARGONE | 33KV P.S.1 SASLIYA | VII-A | OFF | 13 Mar 26 | 10:30:17 | 0 | 13 Feb 26 | 11:43:26 | 0 |
| 132KV BARWANI | 110 | D5 | BARWANI | 33KV BIJASAN | VII-A | ON | 10 Sep 26 | 20:59:19 | 0.0202 | 18 Jun 26 | 17:13:18 | 0 |
| 132KV MANAWAR | 109 | D6 | DHAR | 33KV D.C.L. | VII-A | ON | 10 Sep 26 | 21:00:19 | 0.0053 | 12 Aug 26 | 12:47:20 | 0 |
| 132KV RAJGARH | 105 | D6 | DHAR | 33KV P.H.E. | VII-A | ON | 10 Sep 26 | 21:03:13 | 0.156 | 17 Aug 26 | 12:20:13 | 0 |
| 132KV SINGHANA | 339 | D6 | DHAR | 33KV BARKHEDA | VII-A | ON | 10 Sep 26 | 21:00:08 | 0.0219 | 14 Jul 26 | 16:49:08 | 0 |
| 220KV KUKSHI | 106 | D6 | DHAR | 33KV WATER WORKS | VII-A | ON | 10 Sep 26 | 21:01:06 | 0.2508 | 09 Sep 26 | 03:26:06 | 0 |
| 220KV KUKSHI | 106 | D6 | DHAR | 33KV P.H.E. | VII-A | ON | 10 Sep 26 | 21:01:12 | 2.6902 | 09 Sep 26 | 07:14:11 | 0 |
| 220KV PITHAMPUR_SEC1 | 104 | D6 | DHAR | 33KV SAGORE | VII-A | ON | 10 Sep 26 | 20:38:16 | 1.836 | 08 Sep 26 | 03:00:16 | 0 |
| 220KV PITHAMPUR_SEC3 | 102 | D6 | DHAR | 33KV L.T.INDUSTRIES | VII-A | ON | 10 Sep 26 | 21:01:21 | 16.44 | 07 Sep 26 | 21:35:23 | 0 |
| 220KV RAJGARH2 | 112 | D6 | DHAR | 33KV P.G.C.I.L. | VII-A | ON | 10 Sep 26 | 20:58:16 | 0.1323 | 03 Sep 26 | 12:11:19 | 0 |
| 132KV PETLAWAD | 230 | D7 | JHABUA | 33KV PETLAWAD | VII-A | ON | 10 Sep 26 | 20:54:18 | 3.408 | 05 Aug 26 | 02:59:15 | 0 |
| 132KV RAJGARH | 105 | D7 | JHABUA | 33KV BHARAT OMAN | VII-A | ON | 10 Sep 26 | 21:03:15 | 0.0188 | 04 Sep 26 | 10:26:41 | 0 |
| 220KV RAJGARH2 | 112 | D7 | JHABUA | 33KV BHARAT OMAN | VII-A | ON | 02 Jan 26 | 11:55:12 | 0 | 29 Dec 25 | 16:10:13 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV JOBAT FATA DAM | VII-A | ON | 10 Sep 26 | 21:01:14 | 4.9333 | 02 Jul 26 | 17:06:15 | 0 |
| 132KV ALIRAJPUR | 113 | D8 | ALIRAJPUR | 33KV N.V.D.A. | VII-A | ON | 10 Sep 26 | 21:01:19 | 1.3816 | 18 Feb 26 | 14:57:20 | 0 |
| 132KV BHERUGARH | 294 | D9 | UJJAIN | 33KV NARMADA KSHIPRA | VII-A | ON | 10 Sep 26 | 21:01:09 | 0.0662 | 01 Jun 26 | 16:32:09 | 0 |
| 132KV GHONSLA | 212 | D9 | UJJAIN | 33KV NAVODAYA | VII-A | ON | 10 Sep 26 | 20:59:12 | 1.216 | 25 Aug 26 | 14:52:16 | 0 |
| 132KV RATADIYA | 61 | D9 | UJJAIN | 33KV AMBODIYA | VII-A | ON | 07 Sep 26 | 21:15:20 | 0 | 07 May 26 | 14:15:12 | 0 |
| Total | | | | | | | | | 108.2138 | | | 0 |
|
|
|
|
|
|
|